Tuesday, August 28, 2007

A Note From Our Designer

Matt:

The work in the pantry was limited to removing and replacing the shelving and running new electrical to install a light fixture (supplied by you). We had not planned on removing or replacing the flooring in this area. Should you wish to replace the floor, I would suggest that tile be used. It would be continuous in look with the back hall area. Please advise if you would like to proceed with this. I would need to explore costs.

We are bringing in approx. 6 slabs of Black Galaxy, for you and other customers. If you would like, you could come in and take a look at what we have and tag the pieces with your name. This is not a requirement and you know I will make sure I pick out the best materials for you.

Demolition continued today—there was (3) layers of wood floor underlayment below the carpet and padding and vinyl tile! Wow! (A lot more than is usually found).

There will be final demolition tomorrow and the door framing will start taking place. The plumbers are schedule for Thursday and Friday. The electricians are scheduled for Friday and the following Tuesday (no work on Monday). Once we are past the initial “grunt” work and the area has been cleared of debris, a firm schedule can be put into place for all of the work remaining.

The dumpster will be picked up on Wednesday—we will use trash containers to haul away debris after Wednesday. This should make it easier for you to park your cars!

Ray will be calling you yet this afternoon. He would like to meet with you tomorrow morning to discuss some construction related issues that need to be decided upon in order to continue moving forward. I will not be able to be there, as I have an appointment first thing in Menomonee Falls . Ray will fill me in.

After next week, walls will be getting closed up and the kitchen will start to take shape! I will be in touch with Carrie at Kennedy Hahn in regards to appliance delivery.

We continue to move forward in a positive way…..

Regards,

Jill

No comments: