Friday, September 21, 2007

More Details from Jill

Matt—

Thank you for the update.

I have mentioned to Ray that you do not want to consider refinished the floors in the living room and dining room at this time.

Checking on the floor refinishing for foyer and pantry.

Radiators—we do not have access to people who do sand blasting of old finishes on radiators. We will check with the HVAC people, maybe they will have some suggestions.

Schedule for the upcoming week:

Monday—miscellaneous carpentry work (molding, hardware, painting, etc.)

Tuesday—same as above

Wednesday—Electrical finish (including installation of appliances). Subject to confirmation with electrician. Please make sure new hallway light is on site by this time.

Thursday—No work today for our people, show move in for us at State Fair Park (setting up displays).

Friday—countertop installation. I will be out of the office on this day. I will be working at the NARI Fall Remodeling Show at State Fair Park.

Change order—Materials, as needed, are being ordered. Also, the exterior and storm door are non-standard sizes (surprise!). This accounts for price and also lead time—3 weeks to receive…we cannot schedule this portion until we have and ETA on the doors. I will advise.

All for now, have a great weekend!

Jill

No comments: