Hi Matt:

Update on punch list is as follows:

Plumber is scheduled for call back Tuesday after 2:30

Painting in pantry will be done when doors are installed.

Shelves will be touched up at the same time.

Roll tray under cook top can be adjusted the same time as the touch ups.

Microwave can be taken away at that time.

I will have Greg make sure that he brings along shelf clips.

The handrail leading to the basement is installed.

I am kicking around thoughts about the pot rack—I can fax a drawing over for you to take a look at.

I have sent a list to the electrician of items needing to be addressed. He will get back to me tomorrow with a date to finish up.

Appliances—I called the number you gave me when we spoke this morning. A gentleman answered and identified himself as being from American. I gave him the lock box number so he could get into the house to look at the freezer door handle. I do not know if anything could be done by him. The cook top burner has been repaired.

As you and I discussed this morning, the tile was not able to be installed as scheduled. Our supplier sent incorrect product! I am waiting to hear when the replacement tile will arrive so that portion of the job can be completed.

Ray and I are discussing the door schedule. Hopefully, we can work on this area late this week or early next week and then all of the carpentry related items can be addressed at that time.

So, as I sit here this afternoon I wonder where the day has gone. I look at the list of items above and realize I am waiting for responses from a lot of people. I will get back with definite answers tomorrow.

Regards,

Jill

P.S. Attached you will find a floor care sheet faxed over to me from the refinishing company. You may want to keep a copy in your files for your records.